MC & Commissioning Coordinator at J Ray McDermott
Indonesia

MC & Commissioning Coordinator at J Ray McDermott
Indonesia
I have been working for Oil & Gas offshore facilities national and multinational project for 5 years. My first career was instrument engineer at engineering services company for a year and then I joined pre-commissioning and commissioning work of instrumentation and automation with multinational company for several multinational world class project. My technical experience summary as below:
- Instructor of Process Control and DCS training in Instrumentation System Laboratory - ITB Bandung.
- Design instrument specification, data sheet, and installation drawing.
- Pre-installation calibration of instrument and de-energized instrument cable and tube line test.
- Inspection coordinator of instrumentation and control construction work to bring the system on mechanical completion status.
- Function test on energize state all individual transmitter, control valve, on-off valve, SDV, BDV, Fire & Gas, and HVAC Damper. This including verification conventional I/O, HART, and Foundation Fieldbus.
- Running the system 'live' and verify the function of instrumentation and control in integrated system to make sure the performace of Process Control System and Safety Instrumented System.
- Coordinate the official acceptance Dossier of Project Completion.
Pre-commissioning and Commissioning of Instrumentation and Automation Oil & Gas Facilities.
(Public Company; 10,001 or more employees; Oil & Energy industry)
September 2008 — Present (1 year 4 months)
Coordinate the Mechanical Completion & Commissioning work of North Rankin B - Substructure Project.
(Oil & Energy industry)
August 2005 — August 2008 (3 years 1 month)
Mechanical Completion, Pre-Commissioning, and Commissioning work of Instrumentation and Control. The projecta are Su Tu Vang CPP Platform (CLJOC - Vietnam), Arthit CPP Platform (PTT E&P - Thailand).
(Oil & Energy industry)
May 2004 — August 2005 (1 year 4 months)
Engineering Service Company for Oil & Gas Surface Facilities.
My duties are prepare all specification, data sheet, and detail drawing of instrumentation required for construction. The projects are KODECO KE30 and KODECO Poleng CW and DW.
(Higher Education industry)
July 2003 — March 2004 (9 months)
Research Laboratory conducting Process Control and DCS training.
My duty was an instructor to help the trainee to execute sample project using DCS CS1000 Yokogawa.
Bachelor , Instrumentation and Automation , 1999 — 2004